August Jobsite Update
So much has been happening at the IK Bar jobsite in Gypsum… and there are big things happening! Building A is officially topped off, with all roof decking installed and […]
August Jobsite Update Read More »
So much has been happening at the IK Bar jobsite in Gypsum… and there are big things happening! Building A is officially topped off, with all roof decking installed and […]
August Jobsite Update Read More »
So much work is taking place at the jobsite at IK Bar in Gypsum — it’s so exciting to help build with Eagle County School District employees! Read the full
July 2026 Construction Update Read More »
Framing was in full force this month at IK Bar on Building A. The team finished installing first floor SIP panels and moved onto the demising walls between the units.
June Jobsite Update Read More »
We recently held a home dedication ceremony for 17 families who helped build and then buy their Habitat homes at Stratton Flats in Gypsum. If you have not been to
Nighthawk Circle: Part of Habitat’s Long View Read More »
In June as 17 homeowners received keys to their new homes at Stratton Flats, Sarah shared, voice sometimes wavering with emotion — happy and sad — how a Habitat home,
More Homes, More Hope for Habitat Homeowners Read More »
The much-anticipated start of framing has kicked off on the IK Bar site this past month. The concrete, plumbing and excavation teams wrapped up their work on Building A. Clear
May Construction Update Read More »
This month, progress marched along at IK Bar in Gypsum with earthwork and concrete. On Building A, DGO Concrete finishing pouring the foundation walls. Karl’s Coatings then helped spray waterproofing
April Jobsite Update Read More »
Moving to IK Bar + Building has Begun! Starting in April, all Habitat volunteers and contractors will be working at the IK Bar Construction Site. Building A at IK Bar
March Jobsite Update Read More »
The Phase 11 homes at Stratton Flats are nearly finished. Four of the homes were sold to their Habitat owners and moved into during February. The remaining four units are
February Construction Update Read More »
The end is near for the eight homes still under construction at Stratton Flats. After breaking ground in the summer of 2024, the year and a half process is coming
Phase 11 Wrapping Up Read More »